1704.7.1 Subgrade inspection.Immediately prior to placement of the footings, foundations, fill or other supporting materials the special inspector shall determine that the site has been preparedand isin accordance with the approved geotechnical report
Related products
-
TR-1 SPECIAL INSPECTIONS
TR-1 Subsurface Conditions-Fill Placement & In-Place Density (BC 1704.7.2-3)
1704.7.1 Subgrade inspection.Immediately prior to placement of the footings, foundations, fill or other supporting materials the special inspector shall determine that the…
-
TR-1 SPECIAL INSPECTIONS
TR-1 Footing Foundation (BC 109.3.1)
109.3.1 Footing and foundation inspection. Footing and foundation inspections shall be made after excavations for footings are complete and any required reinforcing…
-
TR-1 SPECIAL INSPECTIONS
TR-1 Masonry (BC 1704.5)
1704.5 Masonry construction. Masonry construction shall be inspected and evaluated in accordance with the requirements of this section, depending on the structural…
-
TR-1 SPECIAL INSPECTIONS
TR-1 Structural Steel – Welding BC 1704.3.1
VERIFICATION AND INSPECTION CONTINUOUS PERIODIC REFERENCED STANDARDa BC REFERENCE 1. Material verification of high-strength bolts, nuts and washers: a. Identification markings to…